Abram's Land - Area Structure Plan and Rezoning

See details in the attachment, includes site sign and notice to the Public.
Final reading was approved, June 22, 2010 in the RMWB council chambers. Surveyors are currently on site to determine the legal boundries to transfer the 91 acres to Abrams Development Corporation for site servicing.
Abram contract letter with RMWB in progress, target to go to RMWB for approval and funding Sept 14, 2010. |
|

Abrams Land - Current Status June 14, 2010

Abrams Land Sept 5th, 2010
"Sale of Land has been approved by the Province"
Notice of Land Release
1)Consultations Completed
a) Aboriginal Consultation.
b) Historical Impact Assessment.
c) Environmental Assessment.
d) Public Open House.
e) Site Massing and Operational Plans
f) Traffic Impact Assessment Complete
2) Nov 3, 2009 Province approves land sale to the RMWB.
3) Approval the Area Structure Plan and Rezoning recieved from RMWB.
4) Abrams & RMWB land transfers to be completed by Oct 30,2010.
5) Cost Optimization complete, RMWB Contract Letter and Fundign with the RMWB to go to council for approval Sept 14, 2010.
5) Engineering for detail site plans by CSM Engineering 90 % complete.
- includes, Utilities, Water, Sewer, Storm Water, Roads & grading.
6) Site Clearing and Grubbing to be completed complete Q 2,2011.
7) Site Grading and services installed and completed Q3, 2011
8) Unknown whether AHS will remain as a joint venture member in the developement of this land...gone out for tender without the Abrams land.
8) Landscaping complete and titles transfered to Owners(TBD)
Further Details

Abram's Land Development
Conceptual Plan at the end of Dickens Drive.
see details at the entrances of both Churches. 

Abram's Land Development Corporation: Regional Municipality Wood Buffalo (Community Center), St.John Baptist Parish(Church), Markaz-UI Islam(Mosque), Northern Light Health Region(Healthy Aging Facility), McMurray Gospel Assembly(Church). 


New Parish Facilities

Building Committee, Parish Finance Committee and PPC will begin with:
- BC, Consultation with the Catholic School Board regarding synergies for sharing offices.
- PPC, Finalize strategies for growth & timeline for construction completion.
- PFC, Finalize stratagies for Fundraising
- BC, Consultation with the parishioner to incorporate needs assessment.
- BC, Determine the type of facilities required.
- BC, Establish cost & affordability.
- Determine what to build first - Rectory, Offices, Hall, Church.
- BC, Develop the project schedule and designs.
- PFC, Financial Approval from the Diocese of St. Paul for facilities. 
|